Guide sections
A cable duct and an individual cable clamp can share a profile groove while presenting different fastening tasks. The duct may cover several mounting points; the clamp may need access after nearby cables are installed. Plan the fasteners from those actual interfaces and service steps before combining their quantities into a purchasing list.
Map accessory mounting points before counting nuts
Use the selected accessory drawing to identify its mounting holes or slots and the intended attachment method. Mark which holes are used in the approved layout. Do not derive support spacing, the number of attachments or allowable cable loading from the number of available holes; those decisions belong to the accessory and installation design.
Keep cable-support locations distinct from fastener variants. Several locations may share one approved nut, while visually similar clamps may require different mating hardware. Confirm the accessory-side requirement before selecting candidates from the T-slot fastener catalogue.
Check access in installation and service states
| Location or state | Access question | Planning action |
|---|---|---|
| Duct base before cover fitting | Can the fastener and tool reach each selected mounting point? | Link hardware to the base drawing |
| Duct after cable installation | What covers or contents obstruct later access? | Define the approved service route |
| Individual clamp near another accessory | Is the slot entry or tool approach occupied? | Check the actual neighboring arrangement |
| End-feed nut location | Will a usable profile end remain available? | Schedule loading before access closes |
| Replacement point | Can the required part be replaced by the planned route? | Resolve access before purchase |
Copy the applicable rows into an optional planning sheet and add the location references. Treat initial installation and later service as separate states: access that exists on an empty frame may disappear once the cable route is complete.
Keep hardware out of unverified cable space
Review the fastening arrangement in section where necessary. Identify the specified head, mating nut or projecting stud relative to the duct or clamp geometry. Ask whether the proposed arrangement stays within the accessory's permitted mounting space. Do not assume a shorter bolt or a different head is acceptable without reviewing the complete requirement.
An illustrative conflict is a fastener that can be reached before a duct cover is fitted but cannot be serviced along the planned route afterward. The design question is access, not evidence that the fastener is unsuitable in every installation. Resolve the sequence or layout before issuing the hardware list.
Release a location-based list
Retain the accessory reference, mounting location, approved fastener variant and mating hardware together, then total identical items for purchasing. Add service access notes where the sequence matters. Electrical, fire, cable-support and loading requirements remain with the applicable installation design; the fastening list does not establish compliance.
For sourcing, send your available list through the enquiry page. Where an accessory is not listed, describe its mounting requirement and discuss availability without assuming that a complete cable-support package is already offered.