A split delivery proposal should show what the first receipt enables and what remains for later. Dividing the total quantity into two shipments is not enough if the first shipment lacks a mating component needed for assembly. Start with the buyer's actual build requirement, then ask whether the proposed releases are feasible for the selected order.
Define the useful first delivery
Identify the complete variants and quantities required for the first build or replenishment. Where nuts are purchased with bolts, brackets or other accessories, review which items must arrive together. Label each date as a requested arrival date or a requested dispatch date so the supplier is not asked to interpret one as the other.
Separate the firm order from later forecasts. An anticipated second requirement is not automatically a purchased balance held for release. State whether the proposal divides one confirmed order or asks for an initial order followed by a possible future purchase.
Create a line-by-line release proposal
| Planning field | Enter for each proposed delivery | Question to resolve |
|---|---|---|
| Item and quantity | PO line, exact variant and pieces | Do proposed releases add up to the ordered quantity? |
| Required timing | Requested dispatch or arrival date | What schedule can actually be agreed? |
| Destination | Receiving location and contact | Are delivery scope and documents different? |
| Assembly dependency | Items that must arrive together | Would an incomplete set prevent the planned work? |
| Remaining balance | Quantity still awaiting release | Who authorizes release and by what date? |
| Commercial basis | Packing, freight and any holding proposal | Which additional costs or conditions apply? |
Treat this table as a proposal until the supplier confirms the scope. Do not assume that completed goods can be stored indefinitely, that a later release retains the original freight price, or that a total-order price applies unchanged to separately placed purchases.
Compare the split against one shipment
Ask for the differences in packaging, freight, documentation, payment and any agreed storage arrangement. Keep product cost changes separate from shipment-related charges. If an early delivery is optional, request a comparison with the consolidated alternative so purchasing can see the cost of bringing that requirement forward.
Confirm what happens if one line is not ready when a release is due: wait for the set, change the release contents or reconsider the schedule. Name the buyer contact who can approve that choice. Avoid a broad instruction to send whatever is ready when missing parts would make the delivery unusable.
Track dispatches and receipts separately
After agreement, retain a release reference against each packing list and update both dispatched and received quantities. A shipped quantity is not yet a confirmed receipt. Carry shortages or unresolved differences separately rather than silently reducing the remaining order balance. Share the available list through the sourcing page; split delivery remains an order-specific arrangement to discuss and confirm.