Guide sections
Compare prices only after each offer identifies the same requested item, quantity and supply scope. Keep the buyer's requirement beside the supplier's response: an alternative material or an excluded service should remain visible when you rank the offers.
Establish the item being compared
For example, the listed sliding nut XAHN21-308-6 identifies a carbon-steel, zinc-plated variant for EU 30, slot 8 mm, with an M6 thread. XAHN31-308-6 is the SUS304, vibratory-polished alternative in that catalogue row. The shared series and thread do not make a material change an equivalent quotation. This is a catalogue example, not an actual supplier offer or a fit approval. Use the steel versus stainless-steel comparison to review a proposed material change.
Use the sliding-nut specification table or the T-slot nuts and bolts catalogue to identify the family. Keep the full code, actual profile reference, applicable drawing revision, material and finish together. Ask suppliers to list any deviation rather than replacing your requested specification with their proposed code.
Copy this quote comparison worksheet
Use one sheet per requested variant. Record what each quotation actually says; leave unanswered fields open.
| Comparison field | Buyer requirement | Offer A | Offer B |
|---|---|---|---|
| Quote reference, date and validity | ___ | ___ | ___ |
| Full variant, thread and profile/drawing reference | ___ | ___ | ___ |
| Material and finish | ___ | ___ | ___ |
| Quantity, unit and pricing quantity | ___ | ___ | ___ |
| Unit price and currency | ___ | ___ | ___ |
| Packaging, labels and included hardware | ___ | ___ | ___ |
| Required checks and documentation | ___ | ___ | ___ |
| Delivery scope, extra charges and exclusions | ___ | ___ | ___ |
| Proposed timing and its starting condition | ___ | ___ | ___ |
| Deviations and unanswered questions | ___ | ___ | ___ |
Resolve differences before ranking prices
| Difference in an offer | How to treat it |
|---|---|
| XAHN31-308-6 offered against XAHN21-308-6 | Material/finish deviation: review the alternative before comparing prices |
| Same requested variant, different pricing quantity | Commercial difference: request a common quantity basis |
| Freight or required documentation left unanswered | Incomplete scope: obtain an answer before treating the total as comparable |
For comparable offers, multiply quantity by unit price and add separately quoted charges once. An unknown freight charge is not zero. Keep currencies and delivery scopes consistent, and record the exchange-rate date if you convert prices. For the wider receiving, inventory and coordination decision, use the total purchase cost guide.
Check MOQ, price-break quantity and total order value separately; combining items does not automatically give every line the same price tier. Use the quote-scope guide when wording such as standard packing or certificate available leaves a deliverable unclear. Sinsdar can request material certificates from suppliers but does not hold them for every product. Third-party testing may be possible, subject to confirmation.
Record the decision and its conditions
Retain the selected quotation version, accepted deviations and open conditions together. If the offers cover different supply arrangements, compare the responsibilities of one sourcing partner and multiple suppliers as well. If clarification changes the price or item, compare the revised offer rather than copying its price into the old record.
For a sourcing enquiry with Sinsdar, send your existing model, drawing or purchase list. The worksheet is for evaluating quotations; completing it is not a condition of making contact.